Ivy May Close, St Annes

Client: Bristol City Council

Built on the former Bristol City Council depot site, our development of five two-bedroom bungalows is located off of Guildford Road in St Annes.

These five homes were constructed with Beam & Block floors and masonry cavity walls with a render finish. The roofs were erected using cassette trusses and finished with concrete roof tiles.

External work proved challenging as there was a need for a sustainable urban drainage system, along with a large retaining wall and relocation of Western Power cables.

Guildford Road bungalows 2_DSC0773_DSC0767Guildford Road bungalows 4_DSC0896

This project was certified by LABC, with air permeability and acoustic test results proving impressive, leaving future residents to enjoy these new homes in comfort.